Gantt Chart with Dependencies — Schedules That Reschedule Themselves

Link tasks with real dependencies — Finish-to-Start and the other three types — and your timeline stops being a drawing. When one task slips, everything downstream moves, the critical path recomputes, and the end date tells the truth.

Build my Gantt freeAlready have tasks in Excel? Import them →
P
Project Phoenix: Enterprise API Integration & UX Refresh
Search tasks, epics, or team members…
Save
Weeks
Months
Epic
Team
Dep. lines
Optimization (6d saveable)
+ Task
+ Epic
TIMELINE: MAY 2026 - JUL 2026
Deadline:dd/mm/yyyy
EPIC / TASK NAME
MAY 26Week 20
MAY 26Week 21
MAY 26Week 22
JUN 26Week 23
JUN 26Week 24
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
1
2
3
4
5
6
7
8
9
10
Phase 1: Discovery & Scoping4
Phase 1: Discovery & Scoping
Stakeholder Requirement Elicita…
Project Manager
Stakeholder Requirement Elicita…
Project Manager
Existing Tech Stack Audit
Architect
Existing Tech Stack Audit
Architect
Capability Gap Analysis
Project Manager
Capability Gap Analysis
Project Manager
M: Scoping Document A…
Project Manager
Project Manager
Phase 2: Estimation & Resource Modelling4
Phase 2: Estimation & Resource Modelling
ROM Estimation
Architect
ROM Estimation
Architect
Resource Capacity Mapping
Project Manager
Resource Capacity Mapping
Project Manager
Risk Assessment & Conting…
Project Manager
Risk Assessment & Conting…
Project Manager
M: Budget Baseline Fina…
Project Manager
Project Manager
Phase 3: The Bid & Proposal4
Phase 3: The Bid & Proposal
Draft SOW
Project Manager
Draft SOW
Project Manager

What are the four dependency types in a Gantt chart?

Dependencies are what turn a task list into a schedule. Axioplan supports all four types — you'll use Finish-to-Start most of the time, but the other three exist for the plans that genuinely need them.

FS
Finish-to-Start

Task B can only start after Task A finishes. The workhorse — "Design must complete before Development begins." Most schedules are 90%+ FS.

Design → Development
SS
Start-to-Start

Task B can only start once Task A has started. For parallel streams that must kick off together — "Testing can begin when Development begins."

Dev ⇄ Testing
FF
Finish-to-Finish

Task B can only finish when Task A finishes. Common for review cycles — "Documentation finishes when QA finishes."

QA ⇄ Docs
SF
Start-to-Finish

Task B can only finish once Task A starts. Rarely used — mostly just-in-time handovers where the old thing runs until the new thing is live.

Night shift → Day shift

How do dependencies change what a Gantt chart can do?

A Gantt chart without dependencies is a picture of your plan. With them, it becomes a model — one that answers questions instead of just displaying bars.

The critical path, computed

The chain of dependent tasks that determines your end date is highlighted automatically. A slip on the critical path moves the deadline; a slip anywhere else gets absorbed by slack.

Live what-if scenarios

Drag a task, add a dependency, or change an estimate and the whole schedule recomputes in real time — including on a client call, when the scope question actually lands.

Dates with confidence levels

Because every task carries a PERT estimate, the end date isn't one number — it's a P50 and a P85. You know which date to aim for and which one to commit to.

Planning people as well as tasks? Dependencies pair with resource allocation on the same Gantt so a schedule that's technically feasible is also staffable.

Is there a free Gantt chart with dependencies?

Yes — and not a hollowed-out one. Most tools put dependencies behind a paywall or a 14-day trial. Axioplan's free plan is a real plan: dependencies, critical path, and probabilistic estimates included, forever.

If your task list lives in a spreadsheet today, the free Excel to Gantt converter gets it onto the chart in about a minute. Prefer to stay in the spreadsheet? Our guide to building an Excel Gantt chart with dependencies covers the formula approach — and where it stops scaling.

Free plan includes
One project with unlimited tasks
All four dependency types (FS, SS, FF, SF)
Unlimited team members — no per-seat fees
PERT estimates with P50/P85/P95 confidence dates
Read-only share links for clients

Frequently asked questions

Common questions about Gantt charts with task dependencies.

Map your next bid with mathematical certainty.

Play with the scenarios, model your team, and lock in your strategy.
Your first project is on us, forever.